14.03.2012
After the minor delays caused by the extreme weather conditions in this year, the construction works at the 80 MW wind farm Mihai Viteazu have been taken up again.
As of mid-March 2012, a total number of 32 of the 40 planned Gamesa G87 wind turbines have been completely installed. Out of these, already 14 units are connected to the grid and producing electricity.
The project owner, Iberdrola Renewables Romania Srl., planes to conclude the test operation phase of the wind farm by April 2012, so that the definitive commissioning of the 40 machines can take place in May 2012.
This is to inform interested parties that since April 10, 2013, our company has a new distri-bution of its Shareholdersmore
The four wind energy projects at Mihai Viteazu, Romania, which the Swiss company NEK Umwelttechnik AG developed for us during the past years and which we sold to Iberdrola Renovables, S.A., are now fully operational.more